North abutment installed on 216th Avenue bridge; crews to set superstructure before 24th Street work
Summary
County engineering reported progress on the 216th Avenue bridge replacement: the north abutment is installed and the south abutment is being set; crews will set beams and superstructure before moving to the next scheduled road project, with winter scheduling constraints noted.
Get email alerts on the Bridge Replacement topic
No spam. Unsubscribe anytime.
County engineering staff updated the board on the day-labor bridge replacement on 216th Avenue, reporting that the north abutment is installed and crews are working on the south abutment. Staff said they plan to set beams and the superstructure on the 216th Avenue crossing before moving to 24th Street work.
"The north abutment is installed. The south abutment is currently being installed," the county engineer said, outlining the phased work. Staff said they will coordinate scheduling with county personnel and that further shoulder and washboard repairs are underway on other highway segments. The board discussed timing and noted winter weather is approaching, which could affect the schedule. No formal action was taken; this was an informational update.