County weighs assistance after Miles reports collapsing storm sewer under Ferry Road; engineer estimates about $30,000
Summary
The county engineer reported a collapsed 24-inch storm sewer under Ferry Road (500 Avenue) in the city of Miles and provided a rough cost estimate of about $30,000 (including contingency); the board asked staff to gather more information about the city's FM/RCTP funds and possible payback terms before deciding.
Get email alerts on the Stormwater topic
No spam. Unsubscribe anytime.
Jayden Shekel, representing the engineer's office, told supervisors that a 24-inch clay storm sewer pipe running under Ferry Road (500 Avenue) in the city of Miles is collapsing and that the county received a request for assistance. "About $30,000, and I include some contingency," the engineer said when describing the preliminary estimate for replacement from inlet to inlet.
Board members discussed options: the county could contract for the repair and withhold the city's FM-extension funds until reimbursed, the city could pursue RCTP (regional) funding next year, or temporary patches or gravel could be used short-term. Supervisors asked staff to check how much FM/RCTP money Miles has received in recent years and to prepare proposed terms (including payback schedules) for the board to consider at a future meeting before the county commits funds for the repair.