PPUD closes Well 4A construction; approves design task order for TCP treatment

Pixley Public Utility District Board · July 22, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

PPUD filed a Notice of Completion for Well 4A and submitted reimbursement requests; the board approved Task Order 26-01 with Provost & Pritchard to provide final design and construction-phase services for the TCP treatment project and directed staff to explore an RCAC bridge loan or internal bridging for interim payments.

District Engineer Maija Madec reported construction of Well 4A under the DWR Drought Relief Grant is complete and a Notice of Completion was filed with Tulare County on May 27, 2026; closeout documentation and final reimbursement requests were prepared and submitted to the Department of Water Resources. Staff noted intermittent pressure-sensor settings had caused high-pressure lockouts; the high-pressure alarm had been changed from 50 psi to 70 psi and will be removed when pressure stabilizes at 60 psi; low-pressure alarm is set at 35 psi. A blown fuse discovered after a power loss was replaced by a Turnupseed technician.

Separately, the State Water Resources Control Board issued a revised Construction Funding Agreement for the TCP treatment project; PPUD signed and the State executed the agreement on July 15, 2026. The board unanimously approved Task Order 26-01 authorizing Provost & Pritchard to prepare final design and construction-phase services for TCP treatment and directed staff to pursue options for interim financing (RCAC bridge loan or borrowing from the TCP account) to avoid unfavorable interest costs.