Plumbing and finish work scheduled this week for science lab
Summary
The committee reported that delayed plumbing will be installed later in the week and that ceiling tiles, ductwork and a drop electrical cord are also scheduled as part of finishing work for the renovated science room.
Get email alerts on the Construction Schedule topic
No spam. Unsubscribe anytime.
During its Aug. 4 special meeting the LCS Science Room Building Committee reviewed remaining tasks for the science-lab renovation and confirmed near-term work. Members recorded that plumbing, which had been delayed, is due for installation later that week; ceiling tiles, ductwork and a drop electrical cord are also scheduled to be completed as part of the final finishes.
Committee members noted these tasks as part of the completion timeline and did not record a vote on scheduling. The minutes do not specify exact contractor names for the plumbing and finish trades or the precise completion dates beyond indicating the work was planned for the coming days.