Summary
Public Works reported 22 active CIP projects including a near-complete University Avenue pedestrian overcrossing with an October target for completion, traffic calming moving to kickoff after insurance issues were resolved and Newell-Bridal construction beginning with environmental restrictions pausing channel work until spring.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Public Works Director Hamza Javed gave the council a quarterly update on the city's capital improvement program, reporting 22 active projects across conceptual, design, construction and closeout phases.
Javed highlighted the University Avenue pedestrian overcrossing as the largest current project and said it is nearing construction completion with a tentative end-of-October finish and a planned ribbon-cutting. He said final striping and bike-lane enhancements remain to be completed in the project's final phases. The traffic calming project, which faced delays related to insurance documentation for the contractor, recently cleared those issues and had a kickoff construction meeting scheduled. Javed also described the Newell-Bridal project that Palo Alto is leading; tree trimming has started while environmental restrictions will pause some in-channel work until spring.
Councilmembers raised cyclist-safety concerns at overcrossing approaches and asked staff to pursue additional striping, green bike lanes and other mitigations; staff said stripe work and bike boxes are planned as part of final project phases. Council also pressed the contractor punch list for earlier repaving work (Runnymede), and staff said deficiencies are on a punch list and payments have not been released while corrective work is completed.
Speakers (attribution whitelist): [{"name":"Hamza Javed","role_title":"Public Works Director","affiliation_type":"government","affiliation_name":"City of East Palo Alto","first_reference":{"block_id_start":"SEG 1421"}}]
Provenance: topicintro: {"block_id_start":"SEG 1421","block_id_end":"SEG 1446","evidence_excerpt":"The city of East Palo Alto has an active capital improvement plan ... Currently, in this fiscal year, we have 22 active projects.","reason_code":"topicintro"}, topfinish: {"block_id_start":"SEG 1560","block_id_end":"SEG 1560","evidence_excerpt":"... pedestrian overcrossing at University Avenue and the 101. We are nearing construction completion.","reason_code":"topicfinish"}