Board approves final payment and release of retainage for Lakeview Avenue reconstruction
Summary
The town approved final payment and release of retention for the Lakeview Avenue reconstruction project after the town engineer certified completion; the board discussed apparent differences between the original performance security and the final contract amount before voting to carry the motion.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
The Town of Orchard Park board approved a resolution accepting the final change order, authorizing final payment and releasing performance security for the Lakeview Avenue reconstruction project, which the town engineer reported was completed on June 26, 2025.
During questions, a board member asked why the performance security and final contract amounts appeared to differ. The town engineer explained the performance security reflected the original bid amount, while the final contract decreased after itemized change orders. After that clarification the board voted to approve the final payment and release the retention to Bauer Construction; the motion carried.