Elkton public works reports waterline progress, plans sewer replacements; estimates $200,000 savings
Summary
Public Works Director Gaither Hurt reported Blue and Gold Drive water‑line repairs are about 45% complete, Phase 2 bids are due Aug. 13, 2025, and upcoming sewer replacements on several streets will be done in‑house, saving the town about $200,000.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Public Works Director Gaither Hurt told the council that the Blue and Gold Drive water‑line repair is approximately 45% complete and that Phase 2 bids are due Aug. 13, 2025. He said sewer line replacement work on Jackson Avenue, W. Prospect, W. Summit, Fairfax and W. Marshall will follow, with the Public Works Department performing the work in‑house.
Hurt said performing the sewer work internally "would save the Town about $200,000." Council members received the status report; no award or new appropriation was taken at this meeting.