Olney says sewer-pond solar project remains in Ameren interconnection queue

Olney City Council · August 26, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Officials reported the separate solar installation at the sewer pond is still in Ameren's interconnection queue; Chair said the queue is long and the city currently receives an annual (not monthly) payment from that arrangement.

Council members asked whether the city's sewer-pond solar installation is still active. The chair confirmed the project is still moving through the interconnection process with Ameren and that the queue is long. He also said the city receives an annual payment from the arrangement rather than a monthly stipend.

"I spoke with Andrew, a few weeks ago seeing where they were at in the queue for Ameren," the chair said. He added that the project "is still in process" despite the long queue and that staff have answered the company's questions about the site.