Council accepts East Centennial Blvd project, approves $10,583.36 retainage payment

Lindale City Council · April 7, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council accepted East Centennial Blvd, starting the two-year warranty, noted a net underrun of $60,836.61 on the project, and approved payment #19 (retainage) of $10,583.36 to A.E. Shull and Company.

The Lindale City Council voted April 7, 2026 to accept the East Centennial Boulevard project after receiving a letter of completion from the city engineers. City Manager Carolyn Caldwell told the council the acceptance will commence the project’s two-year warranty period and that the project experienced a net underrun of $60,836.61 compared with the original contract.

Following that report, Councilmember Greg Kilgore moved to accept the East Centennial Blvd project and approve payment #19 (retainage) in the amount of $10,583.36 to A.E. Shull and Company; the motion was seconded by Bryan Summerville and carried unanimously. The council’s vote authorizes the release of the specified retainage to the contractor and documents the contract underrun in the minutes.

Staff did not present additional line-item accounting in the meeting minutes; follow-up by the city engineering or finance staff may provide more detail on how the underrun affects remaining project budgets.