Union Town Square change order routed to city is tabled; owner's agent to negotiate revisions

City of Union Commission · September 3, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Summit Architects + Engineers, acting as the owner's agent, recommended tabling a contractor change‑order request for Union Town Square until Summit meets the contractor; a revised, lower‑cost change order is expected Sept. 16.

Scott Noel, president and CEO of Summit Architects + Engineers, told commissioners that Summit was hired to act as the owner's agent on the Union Town Square project and that a contractor’s change‑order request reached the city before Summit had the opportunity to review it. Summit recommended no action be taken on the current change order and said Summit would meet with the contractor to resolve communication and scope issues. Noel said a new change order with a lower dollar amount will be presented at the Sept. 16 caucus meeting for the commission’s consideration.

Attorney Greg Voss explained the procedural error that prompted Summit’s recommendation and confirmed Summit’s role as the trusted advisor on the project. The commission accepted the recommendation to table action and directed staff and Summit to report back with the revised change order.