Zoning board grants extension for 20 Parkway Road, sets firm start and finish dates
Summary
The Bronxville Zoning Board of Appeals granted an extension to the owners of 20 Parkway Road to demolish the existing building and construct three townhouses, requiring demolition to begin by Oct. 31, 2026, and completion by Oct. 31, 2028. Members warned this is likely the final extension and demanded contractor and financing documentation.
Get email alerts on the 20 Parkway topic
No spam. Unsubscribe anytime.
The Bronxville Zoning Board of Appeals voted unanimously to grant an extension to the owners of 20 Parkway Road to demolish a two‑story multifamily residence and build three townhouses, setting demolition to begin by Oct. 31, 2026, and completion by Oct. 31, 2028. Chair Stuart McIntosh proposed the resolution tying the dates to planning board approval and the board approved it after discussion.
Owner Lauren Krause told the board she had moved the project through a lengthy series of technical and financial hurdles, including updates to meet the 2025 building code and asbestos remediation. "As of May 15, we got our clearance certification from the state of New York," Krause said, adding that the team had resubmitted revised drawings to the lender and that a final contractor bid and a utility shutoff letter remained outstanding. She said earlier underwriting from TD Bank fell through and that Orange Bank is now the lender pending final underwriting documents.
Board members pressed for concrete milestones. Charlie Law expressed frustration with repeated delays, saying, "it just doesn't seem like there's any fire underneath this project," and warned he would be unlikely to grant another extension. McIntosh and other members echoed that tone, urging Krause to present contractor contracts, financing commitments and asbestos closeout paperwork if she returns for future relief.
The board noted timing and permit constraints: staff explained asbestos remediation must be closed out before demolition and that a common six‑month state timeframe applies for starting work after permit issuance or the application may be withdrawn and must be resubmitted. The board tied the extension to planning board dates and emphasized its expectation that the owner will accelerate work.
Action taken: the board approved the extension resolution proposed by Chair Stuart McIntosh. Vote: Mary Ellen Carpenter — yes; John Brown — yes; Charlie Law — yes (reluctant); Stuart McIntosh — yes. Outcome: approved.