Council closes public hearing on Davy Crockett CDBG water-line project; construction complete
Summary
Council held a public hearing on the city's 2021 Texas CDBG grant (CDV21-0094) for the Davy Crockett water line and was told construction is complete, the engineer performed the final inspection, and staff is preparing closeout documents.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
The Log Cabin City Council formally opened a public hearing at 7:04 p.m. on Nov. 21 to review work completed under the city's 2021 Texas Community Development Block Grant (CDV21-0094) for the Davy Crockett water line. Mayor Jennifer Williams said construction is complete, the engineer has finished the final inspection, and the City is working on the final closeout documents.
A resident asked whether the hearing covered a separate proposed water line; council members clarified the hearing pertained only to the Davy Crockett line. Councilmember Randy Page said the project "has gone well" and that, although it took time to start, construction moved quickly once underway. No public opposition or further comments were offered, and Mayor Williams closed the hearing at 7:06 p.m.
The hearing record notes staff will continue required closeout steps for the CDBG grant. The agenda item was purely informational and no vote or further action was taken at the meeting.