County staff report 49 JOC projects, high local-contractor use in quarterly update

Capital Improvement Committee, Monterey County Board of Supervisors · August 10, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public Works Assistant Director Lindsay Larable told the Capital Improvement Committee the JOC program issued 49 notices to proceed in April–June FY26, with roughly $2.5 million in facilities work and $6.3 million in public-works construction; staff reported strong local-contractor utilization and said they will include photos in the next report.

The Capital Improvement Committee heard a quarterly job-order-contracting (JOC) status report from Public Works Assistant Director Lindsay Larable, who said the county issued notices to proceed on 49 projects during the April–June FY26 reporting period.

"We had a total of 49 projects that were issued notice to proceed," Larable said, reporting 17 facilities projects with about $2,500,000 in construction value and 32 public-works projects totaling about $6,300,000. Larable told supervisors the report shows a 5% "Guardian" license fee applied to construction value (reported as about $126,000 for facilities and roughly $303,000 for public works) and that local contractors performed the large majority of the work (stated at about 80–82% for facilities projects and 100% for public-works projects during the period).

The update emphasized procurement and local-hire outcomes. Larable said some projects used an optional construction-management fee (JOC Plus) at approximately 5.95% of construction value, and other, smaller projects are tracked on the JOC list even if they do not appear in the large-dollar-item report. County staff said future CIC reporting will integrate these JOC figures with the county's broader capital-projects report and include photos of completed work.

A supervisor asked for clarification about a fund code (ending in 8565) used for certain demolition work; Larable said she would follow up with the specific account information. The committee moved the item by consensus with both members in favor.