Council approved bundled contracts for pool concrete, electrical work and liner after a volunteer update highlighted an unforeseen change order that added roughly $202,100 to the liner contract and outlined remaining electrical, concrete and small-repair tasks.
Get email alerts on the Pool Renovation topic
No spam. Unsubscribe anytime.
The council approved three contracts to continue the city pool renovation project — the concrete contract, the electrical contract and the liner/remissist contract — following a volunteer presentation on work completed and outstanding issues.
Volunteer Jake summarized work completed and unexpected costs, saying, "Basically, that added, about $202,100 dollars to the contract." He reported that electrical work by Diamond Electric and concrete repairs are substantially complete, that the main pool meets an 8-hour turnover rate required for older pools, but that the wading pool pump and some leaks remain to be fixed. Jake also noted remaining items such as diving boards, handrails and perimeter fencing that have quotes and grant considerations.
Chair bundled the three contracts into a single motion; the motion was made and seconded and the council recorded a roll-call vote with all members answering "Yes." During the discussion a council member raised a concern that someone had filled the baby pool overnight and flooded the nearby pickleball court; a councilmember recommended stronger locks and limiting keys to a small set of authorized users. The chair took that security issue under advisement.