City reports sewer line extension and completes Olive Street; reclaimed asphalt to be reused on Mill Street

Lone Oak City Council · November 12, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public Works installed two new manholes and about 400 feet of six-inch sewer line; Olive Street repairs are complete, Arcosa invoiced slightly under estimate, and reclaimed asphalt will be used on Mill Street with a $4,000 private donation pledged toward an $8,000–$10,000 full repair estimate.

Public Works Director Corey Miller told the council crews installed two manholes and roughly 400 feet of six-inch sewer line in four days with no complications. Miller also said the department replaced and added electric lines at the water yard to protect a recently replaced valve from flooding.

Mayor Steve Forgy reported Olive Street work is complete and Arcosa's invoice came in about $300 lower than expected. The Road Funds account showed $36,550 prior to paying the Arcosa invoice. Mayor Forgy said leftover reclaimed asphalt from the Olive Street project will be used to oil-sand Mill Street; a local developer pledged $4,000 toward the work and the County estimates a full Mill Street reconstruction would cost about $8,000 to $10,000.

The County has already worked on Wallace Street and Olive Street and is willing to assist on Mill Street as well.