Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Parks Infrastructure topic

No spam. Unsubscribe anytime.

Engineer presents plan to fix pavilion restroom ponding; epoxy interior and slab replacement proposed

Village of Davis Junction Administrative Board · February 27, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Engineering staff recommended epoxy-flooring and targeted slab replacement with EPDM flashing and re-pitched slabs to resolve ponding at the pavilion restroom; the board discussed warranty, slip resistance and scheduling tied to spring weather and asphalt plant availability.

Engineering staff described a two-part repair for the pavilion restroom and adjacent utility room to address persistent ponding. Inside, the contractor (Partlow) would grind low spots, fill depressions and install an epoxy-textured overlay; outside, the plan calls for removing the existing concrete apron, installing EPDM flashing at the foundation, and pouring new slabs tied to the old with dowel bars and pitched 1–1.5 percent to direct flow away from the building.

“The EPDM, they said, is a self healing, material,” the engineer explained while outlining sealing and double-protection details. Trustees asked about slip resistance for surfaces used by splash-pad patrons; the engineer noted multiple texture/abrading options and offered to provide samples. Board members also raised warranty length: staff said a one-year warranty after completion is typical and that construction oversight would include survey checks to ensure grade and drainage are built as designed.

Construction timing depends on weather; staff said work could begin after consistently above-freezing conditions and that asphalt work tied to site grading may wait until the asphalt plant reopens in mid-May. The objective is to have the work prioritized for spring so drainage issues are resolved before heavy summer use.