Board approves Change Order No. 3 for Gateway Subdivision, delaying paving completion

Davis Junction Board · December 15, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved a change order for Gateway Subdivision infrastructure that delays HMA paving and extends the project completion date by roughly 180 days; the motion passed on roll-call.

The Davis Junction board approved Change Order No. 3 for the Gateway Subdivision infrastructure improvements project, a schedule-only change that delays hot-mix asphalt (HMA) paving and extends the contractor's final completion date by about 180 days.

Chris moved to approve the change order and John seconded; the board discussed that the change order did not add money but extended the schedule, with one member noting it "gives them an extra hundred and 80 days to get it completed." A roll-call vote followed and the motion carried.