Verizon tower work stalled by National Grid electric service delay, board told

Town Board · August 12, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Supervisor Bronner said the planned Verizon tower (Tectonic) is delayed because National Grid has not yet provided electric service to the site; residents had asked about the delay.

Supervisor Bronner reported residents' inquiries about the Tectonic‑installed Verizon tower and said the project is delayed because National Grid has not yet provided electric service for Verizon at the site. The minutes do not record additional technical detail or a timeline; the board recorded the update for information only.

No motion or formal action was recorded; the board did not set a follow‑up date during the meeting. Town officials indicated they would monitor the situation and relay updates when utility service is established.