Sewer District No. 1 nearing completion; board approves $48,000 engineering payment amendment
Summary
Engineers reported the sewer main is nearly installed and pump station complete with construction ~90% finished; the board approved Amendment No. 6 authorizing $48,000 in modified payments to the project's engineer.
Get email alerts on the Sewer Infrastructure topic
No spam. Unsubscribe anytime.
Town engineers told the board that rock sawing for Sewer District No. 1 is approximately complete, about 99% of the main line is installed, and the pump station is finished; overall construction was estimated at about 90% complete with an April 2026 target for remaining work. The minutes state the board is "waiting for the NYSDOT pipe bridge before completion of the Main line."
Separately, the board approved Amendment No. 6—modifications of payments to the engineer for Hounsfield Sewer District 1 in the amount of $48,000 after a motion by Councilwoman Courtney Brown and second by Councilman Chris Lee; the motion carried with all ayes.