Sewer District #1 nearing completion; NYSDOT bridge delay cited
Summary
Board heard that Sewer District #1 construction is approximately 95% complete but remains dependent on a NYSDOT pipe bridge; the latest schedule for bridge completion is Feb. 20, 2026.
Get email alerts on the Sewer Infrastructure topic
No spam. Unsubscribe anytime.
Town consultant Barton & Loguidice updated the board on sewer work related to the district: construction is approximately 95% complete but the main-line finish is pending a NYSDOT pipe bridge. The consultant provided an estimated completion schedule for the bridge of Feb. 20, 2026, which the board noted will affect final completion and commissioning.
The update accompanied action on related water-system contracts; the minutes record coordination tasks and that staff will follow up on the bridge schedule before finalizing the sewer main connection. "Sewer District #1 โ6 Construction is approximately 95% complete. Waiting on NYSDOT pipe bridge before completion of the Main line. The latest schedule update for bridge completion is 2/20/2026," the minutes state.