Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Construction Contracts topic
No spam. Unsubscribe anytime.
Council approves $1.005M change order for Armand CN Railroad culverts after utility conflicts
Summary
Change order No. 1 for the Armand CN Railroad culverts project increased the contract by $1,005,921.76 and added 60 days; staff explained conflicts with utilities and the need for permanent sheet piling, and the council approved the change order with one member absent.
Get email alerts on the Construction Contracts topic
No spam. Unsubscribe anytime.
Council reviewed a substantial change order for the Armand CN Railroad culverts project (project P200801): Change Order No. 1 increases the contract by $1,005,921.76 and extends completion time by 60 days. Project staff said work-change directives were used to keep the contractor working while utility and field location conflicts were resolved.
"Work change directives allow the contractor to move forward with work items that have been negotiated and agreed upon. This process avoids delays and costs associated with work stoppages," the project presenter said, then described major costs stemming from converting sheet piling to permanent installation (nearly $600,000 of the increase) and other necessary adjustments after potholing revealed utilities not where expected. Council members and public commenters raised concerns about recurring large change orders and the difficulty of utility coordination in railroad right-of-way; staff said funds had been identified and explained the railroad—s limits on early potholing and utility locating. The change order passed (vote recorded as passing with the exception of Miss Skiba).
