Parish president outlines multi‑million-dollar drainage, railroad and recreation projects
Summary
Parish President Jewell updated the council on pump station construction (Months 1 & 2), Murray Hill/Deshiran Drive improvements, a $10.5M CN jack-and-bore railroad project, the $4.99M Des Allemands boat launch and a $32M investment in drainage infrastructure.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Parish President Jewell provided a roundup of capital projects under way and nearing completion across the parish. He said work on Months 1 and 2 pump stations is continuing and described stormwater discharge piping installed beneath CC Road; the combined pump-station projects represent a $32 million investment in drainage infrastructure.
"Together, the months 1 and months 2 pump station construction projects represent a $32,000,000 investment in the St. Charles Parish drainage infrastructure," Jewell said, and outlined timetables for substantial completion of several projects: Months 1 expected November 2026, Months 2 in January 2027, and Murray Hill/Deshiran Drive improvements (a $2.1M project) on track for substantial completion by Sept. 1. Jewell also reviewed the $10.5M CN jack-and-bore project (first bore anticipated late August), the $4.99M Des Allemands Boat Launch (NRDA/Restore Act funding), and other drainage center repairs and canal improvements.
Council members asked for neighbor notification about noise and vibration during 24-hour boring operations and raised questions about timelines and utility coordination. Staff pledged to notify adjacent neighbors when jacking operations will occur and said permitting and railroad requirements constrain some pre-construction utility locating work.