WCID No. 1 updates Dickinson City Council on water and sewer capital projects
Summary
WCID No. 1 General Manager Patrick Denar briefed the City Council on major water and wastewater capital projects including water‑line replacements, lift station rehabilitation, force mains, water‑plant work and a multi‑phase sanitary sewer rehabilitation effort.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
WCID No. 1 General Manager Patrick Denar told the Dickinson City Council that the district is advancing a series of water and wastewater capital projects, citing water line replacements, lift station rehabilitation, force main installations, water‑plant rehabilitation and a major sanitary sewer rehabilitation project.
Denar presented the work as a coordinated capital program addressing aging infrastructure and storm‑related vulnerabilities. The department report did not include dollar amounts or construction schedules in the minutes; Councilmembers asked follow‑up questions about traffic and resident communications during subsequent agenda items. “WCID No. 1 Presentation: General Manager Patrick Denar and staff presented updates on major water and wastewater capital projects, including water line replacements, lift station rehabilitation, force main installations, water plant rehabilitation, and a major sanitary sewer rehabilitation project,” the minutes state.
The presentation was given as part of the Department Head Status Report; no formal action or vote on these projects was recorded in the meeting minutes. Councilmembers and staff discussed coordination needs with county entities and state agencies for right‑of‑way and traffic control in later discussion of related roadwork.