City updates council on $13.9M CIP and progress on several infrastructure projects
Summary
Staff reported completion of about $5.3M in CIP projects this fiscal year and described remaining projects totaling approximately $13.9M, including East Jefferson water/sewer upgrades, Hurricane Creek interceptor, Ballard interceptor design and wastewater plant upgrades.
Get email alerts on the Capital Improvement Plan topic
No spam. Unsubscribe anytime.
City staff provided the council an update on the capital improvement plan (CIP), reporting roughly $5.3 million in completed projects so far this fiscal year and outlining projects in design and procurement stages that total about $13.9 million.
Staff said completed work includes sewer‑line replacements, Site 6 ground storage‑tank rehabilitation and leak repairs on an elevated storage tank. Projects in design include East Jefferson water and sewer upgrades (95% design; bid postponed), Hurricane Creek interceptor (30% design; $3.4M estimated total), and Ballard interceptor design ($670,000). "So the project totals $13,900,000 for the CIP projects," staff reported. No council action was required; members thanked staff for progress and cost‑saving measures.