Substation tap changer installed but testing shows a fault; vendor to continue diagnostics

Village of Tupper Lake Board of Trustees · December 16, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Electric Superintendent Michael Dominie reported Black & McDonald installed a substation tap changer but re-testing indicated a fault possibly tied to a bushing or transformer; additional testing will continue until the cause is identified.

Electric Superintendent Michael Dominie said the substation tap changer has been installed by contractor Black & McDonald. During required re-testing, a fault was detected; Dominie said weather can affect accurate readings but that the fault might be caused by a bushing or transformer and that Black & McDonald will continue tests to determine the problem.

Trustees approved the electric monthly report and small account write-offs (approximately $30.37 and $32.31) during the meeting. No operational timeline for repairs was provided; the contractor will keep testing until a root cause is found.