Council approves $1.29 million SCADA upgrade for Gallup Regional Water system
Summary
The council approved a $1,287,141.34 contract and accompanying budget adjustment to upgrade the Gallup Regional Water SCADA system; discussion noted a $250,000 funding shortfall related to the Navajo Gallup Water Supply project cost cap.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Water Superintendent Jan Boone asked the council to approve a contract award to upgrade the Gallup Regional Water Supervisory Control and Data Acquisition (SCADA) system and to authorize a budget adjustment for a reported $250,000 shortfall. Boone presented the contract price as $1,287,141.34 and described enhancements for remote access and real-time data monitoring.
Councilor Sarah Piano moved to approve the proposal and the budget adjustment; Councilor Sierra Yazzie Asamoa-Tutu seconded and the motion passed unanimously. Discussion included clarifying which water system components are covered by the upgrade and how the $250,000 shortfall relates to the Navajo Gallup Water Supply project cost cap; staff provided project clarifications but no further funding sources were specified at the meeting.
Staff will proceed with contract execution and provide follow-up details on implementation timelines and funding reconciliation.