District engineer: stormwater system handled Tropical Storm Debbie but reached capacity; possible drainage connection recommended

River Ridge Community Development District Board of Supervisors · August 27, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Hole Montes engineer reported Pinehurst inlet grate replacement ~80% complete, noted stormwater system flowed but reached capacity after nearly 8 inches of rain, and suggested adding a drainage connection to Lake E1-A to bypass pipes and inlets; an affected resident raised mold concerns, which the engineer said were unlikely caused by standing water.

Charlie Krebs, district engineer with Hole Montes, reported that the MRI project to replace the Pinehurst valley gutter inlet grates is about 80% complete and that he would confirm the schedule for asphalt patching. He described the stormwater system’s performance after Tropical Storm Debbie: the system flowed unobstructed but reached capacity in some areas after parts of the community received almost 8 inches of rain over two to three days (the roads are designed for roughly 5½ inches over 24 hours).

Mr. Krebs suggested The Club could add a drainage connection to Lake E1-A to bypass pipes and inlets if necessary. A resident raised concerns that standing water after the storm was coming up through a slab and causing mold; Mr. Krebs recalled prior comments that standing water had been ongoing and said he did not believe the stormwater was the singular cause, noting that other units had not reported similar issues. The board asked Mr. Long to comment and requested the item be added to the next agenda for further review.