Council approves final payments for Well 5 and well-building work; project under budget by about $15,000

City of Boulder City Council · November 17, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City Engineer Elly Goebel briefed the council on Pay App #6 to Karnath Contracting for well buildings and Pay App #2 to O'Keefe Drilling for Well 5 (final payment). Both payments were approved; Goebel reported roughly $15,000 saved from the original cost estimate on Well 5.

City Engineer Elly Goebel presented two pay applications tied to Phase 1, Schedule A of the water system improvements. Council approved Pay App #6 to Karnath Contracting for progress on the well buildings after Drew Dawson moved and Mike Taylor seconded the motion; the motion carried with four aye votes.

Goebel then explained Pay App #2 to O'Keefe Drilling was the final payment for drilling and development of Well 5 and said "around $15,000 had been saved from the original cost of the well." Dawson moved to approve Pay App #2, Taylor seconded, and the motion carried with four aye votes. The approvals close two current contract payment steps for the water project.