Council takes contractor quotes under advisement for failing vehicle-storage boiler

City of Jasper Council · August 11, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff presented four quotes to replace a failing gas-fired boiler in a vehicle storage building and an alternate 100-gallon water heater; two local firms declined to bid and the council voted to take two quotes under advisement pending further review of alternates and legal considerations.

The council reviewed multiple contractor proposals to replace an aging gas-fired boiler in the vehicle storage building and to consider an alternate 100-gallon hot-water heater. Staff said the existing boiler is "on borrowed time" and that the building also currently lacks hot water.

Schmidt Contracting’s quote, read by staff, included a base price of $20,625 and an alternate amount of $15,975; another bidder quoted $22,500 with an alternate of $11,370. Staff noted two local firms informed the city they would not submit quotes. Council moved to take two quotes under advisement—one from Schmidt and one from Mariner/Mariner’s—and the motion carried by voice vote.

Council members asked clarifying questions about the 100-gallon specification and whether the alternate on-demand unit would meet needs; staff said they would consult with legal and continue research before final selection.