Village approves pay estimate #8, removes fence and revises engineering agreement for water project
Summary
The Village of New Holland approved pay estimate #8 for its water project, voted to remove a fence from the project scope and revised the engineering agreement to follow IEPA guidelines; Nextlink coordination for the new tower was also noted.
Get email alerts on the Water Project topic
No spam. Unsubscribe anytime.
The Village of New Holland board on July 9 approved pay estimate #8 for the village water project and voted to change the project scope by removing a fence, the board’s minutes show.
During the 'Old business' discussion, Eddie Davison moved to approve pay estimate #8 and Jim Shelton seconded; the motion passed unanimously. Shelton later moved to remove the fence from the project scope; Chris Cochran seconded, and the board again voted unanimously to remove the fence. The board also approved a revision to the original engineering agreement to bring it into compliance with IEPA guidelines after Eddie Davison moved and Jim Shelton seconded that motion.
Board members additionally noted that Nextlink must be given coordinates for a new tower so the company can move equipment and update its agreement with the village, a logistical step tied to the infrastructure changes. No dollar amounts for pay estimate #8 or the engineering-contract value were specified in the minutes.