Streets supervisor proposes $75K mill-and-overlay, new truck and continued maintenance schedule
Summary
Street Supervisor Alan Hiller asked the council to budget approximately $75,000 for mill-and-overlay work in 2026, $15,000 for crack filling, $20,000 for dust coating/patching, $12,000 for storm sewer cleaning, $40,000 for snow hauling and equipment rental, and authorization to buy a replacement truck (budgeted $45,000).
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
The streets department presented its prioritized capital and maintenance needs for 2026.
Street Supervisor Alan Hiller requested mill-and-overlay work (~$75,000), crack filling (~$15,000), dust coating/patching (~$20,000), storm-sewer cleaning (~$12,000), and snow-hauling and snowblower rental (~$40,000). He also asked the council to permit purchase of a replacement pickup (two-wheel drive, regular cab, 8-foot box), noting $45,000 was slated in the 2026 budget and vendor quotes checked came in under $40,000.
Hiller recommended skipping this year's seal coating because the current pavement conditions do not justify the minimum service cost (cited as $26,000 minimum). He told council members that crack-sealing and routine maintenance would remain priorities if seal-coating is deferred.