Bucksport pool remains closed after repeated leak tests; deeper repair work planned

Bucksport Economic Development Committee ยท August 11, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff described ongoing work to find and fix a leak in the municipal pool: camera scopes, cut asphalt, new schedule-80 drain piping and repeated refill tests. The pool remains closed while town and volunteers evaluate a next repair step.

The community economic development director explained a sequence of investigative steps and repairs taken after the municipal pool developed a leak. Staff scoped drains with a camera, cut asphalt, installed new 4-inch schedule-80 pipes, puttied and cemented drains, repaved and repainted, and conducted controlled refills, but the pool continued to lose water and remained closed.

"We got it up to 5 feet. We didn't wanna go using too much water. And then an hour a little over an hour to an hour and 0.5, we lost an inch and 0.5 of water again," the community economic development director said, describing repeated tests that failed to identify a definitive repair. She recounted earlier problems in 2020โ€“2023 with broken couplings and said crews tried dye tests, vacuuming and additional camera inspections without conclusive results.

Staff said an additional repair idea is pending volunteers' availability and that scheduling constraints may delay work until September or October. The director said the town has relied on YMCA lifeguard management and an outside pool professional for operations.