City details Phase 2 SCADA upgrades and emergency pump repairs
Summary
Council discussed phase 2 of SCADA and telemetry upgrades for wells and lift stations; staff said Metropolitan Pump Company is the preferred vendor and described replacements of old components, new VFD drives, stainless cabinets and recent emergency repairs that left tower capacity near 25% before restoration.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
City staff outlined a planned Phase 2 upgrade to the city's SCADA and telemetry systems covering wells and lift stations, including electrical upgrades, new flow meters, variable-frequency-drive (VFD) replacements and stainless equipment cabinets.
An agency official described the vendor selection and technical scope: "This brings us up to what we call phase 2 for our SCADEC, system upgrades," and said Metropolitan Pump Company is the preferred provider for repairs and implementation. The official noted older components were reaching the end of their expected life and that variable-speed controllers typically last "overall average 10 to 12 years."
Officials said a recent emergency failure left the water tower operating at roughly a quarter capacity and required about 36 hours to restore full service. Staff recommended replacing obsolete contactor-based starters with VFDs and installing sealed stainless cabinets to reduce future downtime. The council did not take a final purchasing vote during this meeting; staff will return with vendor estimates.