Vineland engineers say stormwater upgrades and pipe replacements planned for Chestnut Avenue

City of Vineland · August 6, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff said stormwater modeling shows undersized pipes and that new basins, larger inlets and replacement of aging terracotta and corrugated metal pipes are part of the plan; a property owner reported a collapsed terracotta pipe and the team said such piping will be replaced.

Residents raised flooding concerns at several locations along Chestnut Avenue; presenters said modeling shows some storm systems are undersized for modern storm events and described proposed drainage fixes. "The proposed stormwater improvements will help mitigate flooding along Chestnut Avenue," Grasso said during the presentation.

A property owner described a camera inspection of a terracotta pipe that is collapsing under his parking lot. He said the pipe is "completely disintegrating." Project staff responded that "any terracotta pipe would be replaced automatically" and that corrugated metal pipe nearing its design life will also be replaced. The team also said they have cleaned and videoed the system as part of the investigation.