Commissioners approve Kellner Ditch change order; engineer cites Indiana bat and spawning windows

Lorain County Board of Commissioners · August 12, 2026

Summary

Lorain County commissioners approved a no-cost change order extending Kellner Ditch completion to Oct. 31, 2026; a county engineer representative said environmental restrictions for the Indiana bat and fish-spawning windows limit when in-water and clearing work can occur.

The Lorain County Board of Commissioners approved Change Order No. 1 for the Kellner Ditch project, extending the completion date from the end of July to Oct. 31, 2026 without any increase in contract price. The motion to approve passed unanimously at the Aug. 11 meeting.

A county engineer representative explained that in addition to calendar days the project must meet "environmental regulation deadlines for the Indiana bat and work in the water," and that narrow permitted windows for in-water work and clearing can force delays when inclement weather reduces available workdays. "It's about time as a change order with no dollar amount associated with it," the representative said, noting the schedule constraints and regulatory requirements.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source