Board approves final plans for 189th Street bridge replacement, project on track for November letting
Summary
The board approved final construction plans for the 189th Street bridge replacement after county engineering said DOT review comments were addressed; with signatures authorized the project is back on track for a November letting.
Get email alerts on the Bridge Replacement 189th topic
No spam. Unsubscribe anytime.
Jaden Shepherd, representing the county engineer’s office, presented final plans for the 189th Street bridge replacement and said the DOT's plan-review comments had been addressed.
“We are now ready. Final plans are prepared...so we are now on track for, November letting,” Shepherd told the board. Supervisors reviewed the submission, confirmed documents were available for signature, and voted to approve final plan certification so the project can proceed to letting.
The presentation noted borings delayed pile design earlier in the process, which briefly pushed the schedule; Shepherd said updated borings cleared the remaining concerns. No new funding or contract awards were decided at the meeting; the vote authorized signatures on the final plans so procurement can proceed.