Detour plans discussed for County Highway H utility relocations; staff to coordinate outreach
Summary
Staff outlined phased pedestrian, bike and vehicle detours for utility relocation work tied to the bridge project, noting sidewalk and trail closures in phases, detector loop removals, and a bus‑only left‑turn stage; staff will meet with communications and police to develop outreach plans.
Get email alerts on the Detours topic
No spam. Unsubscribe anytime.
Staff briefed the committee on phased detours and traffic control plans for the utility relocation work. Ben said the packet includes pedestrian detours and the traffic control plan and warned of significant closures affecting sidewalks, streets and trails as utilities move across the creek and into the new alignment.
Committee members asked whether signal timing would be adjusted when lanes close; staff said they expected to maintain one lane in each direction for much of the work but noted detector loops will be removed during the joint trench effort and that one stage will include a left‑turn restriction except for buses. “I don't believe since we're maintaining a lane in each direction… that there would be any necessary adjustment to the signal timing,” one staff speaker said, while a signal specialist noted loop detectors will be removed and a bus‑only left turn will occur in one stage.
Staff said public outreach will be coordinated tomorrow with communications staff if the plan receives internal sign‑off; committee members urged early signage and police reinforcement at early stages to help users adapt to new patterns. No formal action was required; staff will finalize the communications plan and return as needed.