Board recommends Option C for South 51st Street reconstruction, estimates ~$3.6M

Franklin Board of Public Works · August 12, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

After a consultant presentation, the Franklin Board of Public Works voted to recommend a preferred reconstruction plan (Option C) for South 51st Street featuring 12-foot lanes, 5-foot paved shoulders and turn-lane improvements; staff estimated the project at about $3.5–3.6 million and will forward the recommendation to city council.

The Franklin Board of Public Works overwhelmingly recommended the board endorse a preferred reconstruction alternative — labeled Option C — for South 51st Street on Aug. 11, 2026 following a presentation by city engineering staff and consultants.

Julie Chapman, the consultant presenting design options, told the board: "So what we are proposing to do is put back 12 foot lanes, 5 foot paved shoulders, 2 foot gravel shoulders." Chapman said the design also includes left-turn storage bays at Minnesota (100 feet), Marquette (200 feet) and Evergreen (100 feet), and curb-and-gutter transitions on the east side to collect stormwater into a new storm-sewer system where appropriate. She described trade-offs between retaining ditch conveyance and installing curb-and-gutter connected to storm sewer, and said soil borings and other vertical-profile work are expected to arrive by mid-September.

The consultant presented three alternatives: an in-kind replacement estimated at about $2.8–2.9 million, a 5-foot paved shoulder scheme with fewer turn-lane changes at roughly $3.4 million, and the preferred Option C — the 5-foot shoulder plus additional turn-lane and intersection improvements — estimated at approximately $3.5–3.6 million. An 8-foot paved-shoulder option exceeded $4 million and was not recommended.

Chair Chuck Porter summed up the board’s reaction after discussion and a motion: "After hearing the proposal, we're in agreement that that would be the 1 that we're all in favor of supporting." The board then voted to recommend Option C to city council and directed staff to proceed with the design phase.

Chapman said the preferred plan improves bicycle accommodation by moving from 4-foot paved shoulders to 5-foot paved shoulders and widens lanes from 11 to 12 feet to better serve school buses and other large vehicles. She also flagged signal-equipment impacts at the Rawson intersection and said Milwaukee County — which recently rehabilitated signal hardware there — supports the safety concept but would not contribute funding. Chapman added the cost estimate carries a roughly 30% contingency at the 30% design level to cover unknowns such as soil conditions and potential additional storm infrastructure.

Next steps: staff will proceed to vertical design and complete soil borings before finalizing the bid documents; the board’s recommendation will go to city council at its Tuesday meeting. Construction scheduling aims for a spring start to minimize impacts across two school years.