Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Capital Projects topic

No spam. Unsubscribe anytime.

Leander ISD packet seeks approval of $7.17M GMP #3 for Cedar Park High School modernization

Leander Independent School District Board of Trustees · February 13, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The agenda requests approval of Guaranteed Maximum Price (GMP) #3 of $7,170,365 for the Cedar Park High School Modernization Project, funded by the 2023 bond authorization; the packet lists prior GMPs and a project total of $48,697,401 and names Bartlett Cocke General Contractors.

Jeremy Trimble, M.Arch., Chief Operations Officer, presented background on the Cedar Park High School Modernization Project and requested Board approval of Guaranteed Maximum Price (GMP) #3 in the amount of $7,170,365, funded from the 2023 bond authorization. The packet spells out the GMP line items and shows a summary of GMP 1 ($10,918,545), GMP 2 ($30,608,491) and GMP 3 ($7,170,365), with a project total listed as $48,697,401. The contractor listed is Bartlett Cocke General Contractors.

The agenda materials include a detailed GMP 3 line-item list of packages and specific price elements (for example: PR 010 IDF and Electrical Rooms AC Replacement $682,552; PR 011 PAC $4,496,119; PR 013C Casework Replacement $396,338; Owner allowance $300,000) and a sample motion recommending Board approval. The packet indicates $7,170,365 will be funded by 2023 bond authorization and notes a prior transfer of $7,170,365 from the Vista Ridge High School Modernization Bond Project to Cedar Park HS.