Oak Forest awards $639,000 budgeted contract for Crescent Green lift station improvements; generator alternate included
Summary
Council approved awarding the Crescent Green lift station replacement project to Steve Spiess (base bid $525,000 plus $114,000 generator alternate for total $639,000), and directed staff to add backup generators to upgraded lift stations after recent storm-related power losses; staff noted persistent clogging caused largely by non-biodegradable wipes.
Get email alerts on the Lift Station Improvements topic
No spam. Unsubscribe anytime.
Public Works Director Michael Salamowicz reported the Crescent Green lift station is experiencing operational failures—worn pumps and motors, frequent clogging and scarcity of replacement parts. Four bidders submitted proposals; Steve Spiess submitted the lowest base bid ($525,000) and an alternate for a backup generator ($114,000). Council approved awarding the project with the alternate for a total budgeted award amount of $639,000 (6–0; 1 absent).
Salamowicz said staff confirmed the omission of a physical addendum on some bids was a non-disqualifying formality because all bidders had used the correct supplier specifications. He also noted the city plans to require backup generators for upgraded lift stations after a recent storm left 12 of 14 lift stations without power. On sources of clogging, Salamowicz said, "'Flushable' wipes are not actually flushable," identifying those wipes as a primary cause of pump clogging.