Bandera staff outlines timeline for TxDOT-funded sidewalk project and public input to come in months
Summary
Staff said the advanced funding agreement for the TxDOT sidewalk (TASA) program is under review; consultant WSP will be authorized in 2–3 months and public-input town halls and design work are expected to begin in June with a project start 6–8 months away.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
Staff updated the council on the TxDOT/TA sidewalk AFA process: contract services was reviewing the advanced funding agreement and the consultant (WSP) could receive a work authorization in 2–3 months. Staff said scope definition and public input meetings will follow, and they projected the project timeline at roughly 6–8 months before construction would begin.
Council members asked that downtown Main Street businesses be included in outreach and emphasized timely town-hall scheduling when the consultant and scope are ready. Staff said letters from affected businesses had been received and the city will coordinate the public-input process when the AFA and consultant work authorization are in place.