Committee approves three one-year land-use permit extensions
Summary
The committee unanimously approved one-year extensions for two modular homes (Springwater and Coloma) and a garage permit near Covered Bridge after staff reported delivery delays and site-siting reasons.
Get email alerts on the Land Use Extensions topic
No spam. Unsubscribe anytime.
The committee moved and approved three land-use permit extensions. The Skoglund modular-home permit in the town of Springwater (foundation complete; delivery delayed) had expired July 31; the applicant requested a one-year extension and the committee approved the extension after a motion and second. A second modular-home permit in the town of Coloma (permit expired July 24) similarly received a one-year extension; staff said foundation work was complete but delivery was delayed due to UDC requirements. Finally, a garage permit near Covered Bridge was extended for one year because the applicant delayed construction pending the neighbor's site decision so the garage can function as a buffer.
Each request was presented by the Zoning Administrator and approved on a motion and second with aye votes recorded. These extensions were processed as routine land-use permit timing adjustments rather than policy changes; staff will update permit files to reflect the new expiration dates.