Public Works reports culvert replacements, bridge work and asphalt operations
Summary
Public Works updated commissioners on multiple road projects — culvert replacements north of 1095 and west of Centerville, ingress/egress work on the bridge west of the power plant (2200 Road), asphalt crew activity and return to service of equipment unit 953 at the landfill.
Get email alerts on the Road Maintenance topic
No spam. Unsubscribe anytime.
JD Hanley (S7) provided a roads update describing culvert replacements at several locations, noting six culverts were planned on the north 0.5 of 1095 and four had been installed with two more to complete. He reported completing ingress and egress work on the bridge west of the power plant on 2200 Road and that asphalt crews were working west of Centerville finishing culvert capping and smoothing. Hanley also said county equipment unit 953 is back at the landfill and returned to service.
The report was informational; commissioners did not record additional motions tied to these individual maintenance items during the segment.