Mission CISD board approves Hellas Construction BAFO to resurface Tom Landry and Veterans Memorial tracks

Mission Consolidated Independent School District Board of Trustees · December 4, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Mission CISD Board of Trustees approved a Best and Final Offer from Hellas Construction totaling $876,530.00 to resurface track and field-event areas at Tom Landry and Veterans Memorial high school stadiums; trustees voted 6-0 to enter the contract and staff expect to finalize paperwork within about a week.

The Mission Consolidated Independent School District Board of Trustees on Dec. 4 approved a Best and Final Offer (BAFO) from Hellas Construction to resurface the tracks and field-event areas at Tom Landry High School and Veterans Memorial High School.

Ricardo Rivera, Assistant Superintendent for Operations, told the board the firm’s original proposal was $888,490.00 and the BAFO came in at $876,530.00, a reduction of $11,960.00. Rivera said an embedded contingency allowance of $60,000.00 (split as $30,000 per track) remains in the contract, but administration and the district engineer do not currently expect to use that allowance because the work is a resurfacing. He also listed a project contingency of $837,727.80 and soft costs for engineering and testing of $100,473.00 that are included in the estimate but said the district anticipates savings in those line items.

President Iris Iglesias asked about a start date. Rivera said administration will "work closely with our Legal Counsel on writing that contract" and estimated about seven days to complete the contract draft; the district then will meet with engineer Javier Hinojosa and issue a notice to proceed, "we hope to be doing that within the coming week."

Trustee Petra Ramirez moved to approve the BAFO and enter into the contract with Hellas Construction; Jerry Zamora seconded the motion and the board approved it 6-0.

The approved BAFO amount, the embedded $60,000 allowance, and the cited contingencies were presented on the record by district staff during the meeting. The administration indicated it expects some line-item savings but did not provide a finalized contract at the meeting; the board did not place additional conditions on the approval.

The district project will proceed to contract drafting and issuance of a notice to proceed; no construction start date beyond the expected notice timeline was specified at the meeting.