Board discusses KMI Construction closeout, warns of potential liquidated damages

MUNDAY CISD Board of Trustees · September 22, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trustees said they received previously missing warranties and closeout documents from KMI but described limited movement from the company's new ownership; the district indicated it could seek additional liquidated damages if issues remain unresolved.

The board discussed closing out the district’s outstanding items with KMI Construction during the Sept. 22 meeting, saying communications with the company's new ownership produced little progress. District representatives reported they had received previously missing warranties and closeout paperwork but said several subcontractor and warranty questions remain.

Trustees noted they had offered a settlement and cautioned the district could pursue liquidated damages if outstanding obligations are not resolved. No formal vote on further action was recorded in the public transcript; the board said it would provide additional information if new details become available.