Council approves $3,200 amendment to PFAS feasibility study after irregular Well 5 samples
Summary
After Per- and polyfluoroalkyl substances (PFAS) were detected in the North Pressure Zone and Well 5 produced inconsistent duplicate samples, the council approved a $3,200 amendment to the GeoEngineers contract to add startup and delayed testing, keeping the project under the $120,000 state grant.
Get email alerts on the PFAS topic
No spam. Unsubscribe anytime.
Public Works Engineering Technician Steven Patten reported PFAS had been detected in all three wells in the North Pressure Zone and that Well 5 had yielded inconsistent duplicate samples. To address that, staff proposed Amendment #1 to Contract 320 with GeoEngineers to add startup and delayed testing designed to determine whether flushing the well could reduce PFAS concentrations.
Council approved the amendment, which added $3,200 to the project cost and increased the contract total to $116,700, still under the $120,000 state grant allocated for the feasibility study. Councilor John Lyon moved to approve the amendment and Councilor Destiny Jensen seconded; the motion passed unanimously.