Board approves GMP 3 for new athletics complex; site and drainage cost reported under budget
Summary
Trustees approved the Guaranteed Maximum Price Amendment for the new athletics facilities and authorized the Superintendent to finalize the contract; GMP 3 included a site and drainage breakout of $3,945,349, below the originally budgeted $4.5 million.
Get email alerts on the Athletics topic
No spam. Unsubscribe anytime.
The Board approved the Guaranteed Maximum Price Amendment for Package No. 3 for the New Athletics Project, which includes a turf field, premium seating, home and visitor field houses with amenities, baseball and softball complexes, and an eight-court enclosed tennis facility. Bartlett Cocke and LPA Architects presented final renderings before the Board voted to approve the GMP amendment and to authorize the Superintendent to negotiate and execute the final documents.
GMP 3 included a site and drainage cost breakout of $3,945,349, lower than the previously budgeted $4,500,000; the Board was told the difference will be returned to the district for other 2021 Bond projects. Joel Frederick moved for approval and the motion passed 7-0.