Supervisors approve $571.25 change order and set completion hearing for Drainage District 6
Summary
Board approved change order number 2 for Drainage District 6 (increase of $571.25), approved pay estimate number 1 (staff cited $35,002.20 after retainage), and set a completion hearing for Sept. 8 at 9 a.m.
Get email alerts on the Drainage topic
No spam. Unsubscribe anytime.
Supervisors considered multiple items for Drainage District 6 and approved a small contract change and related pay estimate.
The chair read that "the increase on the contract is $571.25" and a motion to accept change order number 2 was moved and seconded. After additional clarification about the pay estimate amount (staff cited $35,002.20 after retainage adjustments), the board approved the pay estimate and set the completion hearing for Sept. 8 at 9 a.m.