Board approves HWH pay application #4 as admin renovation nears completion
Summary
Trustees approved payment for HWH Pay Application #4 for the Phase I administration renovation project; Central Administration is expected to move in within a couple of weeks, and the motion passed 7-0.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
Greg Pope told the board that Phase I of the 2024 administration renovation project is near completion and that the Central Administration offices will be moving in within a couple of weeks. Following the update, Cari Roberts moved to approve Pay Application #4 to HWH; Jerry Cobb seconded. The motion carried 7-0.
The minutes record the board’s approval of the payment during the Aug. 4 meeting; the payment was processed as part of routine bond-construction project oversight. No dollar amount for Pay Application #4 is specified in the meeting minutes.