Board approves $5.93 million deductive change order, lowering GMP for new intermediate school
Summary
Trustees approved a final deductive change order that reduces the Guaranteed Maximum Price for Magnolia Parkway Intermediate School by $5,929,975, bringing the contract sum to $41,652,996 and leaving the contract time unchanged.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
The Magnolia ISD Board on May 12 approved a final deductive change order with Stewart Builders that reduces the Guaranteed Maximum Price (GMP) for the Magnolia Parkway Intermediate School project by $5,929,975. The school construction GMP was decreased from $47,582,971 to a new contract sum of $41,652,996, according to the AIA change order form included in board materials.
Board materials break the savings into remaining owner allowances ($2,961,260), contractor job savings ($2,773,726), and general conditions savings ($194,989). The finalized change order states the contract time will be unchanged and does not adjust the substantial completion date. Trustee Jordan Blake moved the approval; Trustee David McCarty seconded and the motion carried unanimously.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.